09/20/07: Finalized Calendar, Blog Updated 09/21/07: Posted Specifications/Limitations to Blog 09/24/07: Researched Stick & Shingle Architectural Style, Cedar Shingle Siding Online 09/25/07: Researched Cabinets & Counters Online 09/26/07: Researched Cedar Shingle Siding, Site Visit for Ideas
10/17/07: Pros of Alt Sol #1 10/18/07: Cons of Alt Sol #1 10/19/07: Pros of Alt Sol #2 10/22/07: Cons of Alt Sol #2 10/23/07: Pros of Alt Sol #3 10/24/07: Cons of Alt Sol #3 10/25/07: Chosen Solution, Statement of Intention 10/26/07: Design Board Assembly 10/29/07: Design Board Assembly 10/30/07: Design Board Assembly 10/31/07: DUE Selection/Rejection/Intention, Mentor Contacts, Finishes Board 11/01/07: Formal Presentations 11/02/07: Formal Presentations 11/05/07: Formal Presentations 11/06/07: Formal Presentations 11/07/07: Formal Presentations 11/12/07: Calendar Updates 11/13/07: Calendar Updates
02/06/08: Edited North Elevation Drawing 02/07/08: Edited South Elevation Drawing 02/11/08: Edited South Elevation Drawing 02/12/08: Edited East Elevation 02/13/08: Edited West Elevation 02/14/08: Edited West Elevation
03/06/08: Mark post piles to be cut for foundation. 03/07/08: Begin cutting post piles for foundation. 03/10/08: Complete cutting post piles for foundation. 03/11/08: Begin marking Foamcore to be cut for floors. 03/12/08: Cut Foamcore for first floor and second floor. 03/13/08: Cut Foamcore for first floor walls. 03/14/08: Continue cutting Foamcore for first floor walls. 03/17/08: Finish cutting first floor exterior walls. 03/18/08: Completed press release.
04/01/08: cut walls on band saw 04/02/08: sanded edges of walls to create 45 degree angle 04/03/08: marked doors to be cut, cut doors on band saw 04/04/08: finished cutting pieces on band saw 04/05/08: assembled second floor walls, cut out windows 04/06/08: assembled first floor, pilings, and roof
16 comments:
09/20/07: Finalized Calendar, Blog Updated
09/21/07: Posted Specifications/Limitations to Blog
09/24/07: Researched Stick & Shingle Architectural Style, Cedar Shingle Siding Online
09/25/07: Researched Cabinets & Counters Online
09/26/07: Researched Cedar Shingle Siding, Site Visit for Ideas
09/27/07: Completed Testing Procedures
10/01/07: Mentor Contact, Typed Presentation Outline
10/02/07: Completed Mentor Contact Form, Posted Testing Procedures
10/03/07: Informal Progress update Presentations
10/04/07: Reviewed Alternative Solutions, Revised Testing Procedures
10/05/07: Informal Progress update Presentations
10/09/07: Informal Progress update Presentations
10/10/07: Informal Progress update Presentations, Revised Testing Procedures
10/11/07: Revised Testing Procedures, Posted Revised Testing Procedures
10/12/07: Selection/Rejection Analysis
10/15/07: Mentor Contact, Updated Mentor Contact Forms
10/16/07: Calendar Updates, Mentor Contact Forms
10/17/07: Pros of Alt Sol #1
10/18/07: Cons of Alt Sol #1
10/19/07: Pros of Alt Sol #2
10/22/07: Cons of Alt Sol #2
10/23/07: Pros of Alt Sol #3
10/24/07: Cons of Alt Sol #3
10/25/07: Chosen Solution, Statement of Intention
10/26/07: Design Board Assembly
10/29/07: Design Board Assembly
10/30/07: Design Board Assembly
10/31/07: DUE Selection/Rejection/Intention, Mentor Contacts, Finishes Board
11/01/07: Formal Presentations
11/02/07: Formal Presentations
11/05/07: Formal Presentations
11/06/07: Formal Presentations
11/07/07: Formal Presentations
11/12/07: Calendar Updates
11/13/07: Calendar Updates
11/14/07: Floor Plan 1 Adjustments
11/15/07: Floor Plan 1 Adjustments
11/16/07: Floor Plan 1 Adjustments
11/19/07: Floor Plan 1 Adjustments
11/20/07: Floor Plan 1 Adjustments
11/21/07: Floor Plan 1 Adjustments
11/26/07: Floor Plan 1 Adjustments, Mentor Contact
11/27/07: Floor Plan 1 Adjustments
11/28/07: Plumbing Appliance Schedule
11/29/07: Plumbing Appliance Schedule
12/3/07: Floor Plan 2 Adjustments
12/4/07: Floor Plan 2 Adjustments
12/5/07: Floor Plan 2 Adjustments
12/6/07: Floor Plan 2 Adjustments
12/7/07: Floor Plan 2 Adjustments
12/10/07: Floor Plan 2 Adjustments
12/11/07: Gas Appliance Schedule
12/12/07: Gas Appliance Schedule
12/13/07: Window Schedule
12/14/07: Window Schedule
12/16/07: Door Schedule
12/17/07: Door Schedule
12/18/07: Door Schedule, Front Elevation
12/19/2007: Front Elevation
12/20/2007: Front Elevation
01/02/2008: Cross Section
01/03/2008: Cross Section
01/04/2008: Floor Plan Dimensions
01/07/2008: Floor Plan Dimensions
01/08/2008: Wall Section
01/09/2008: Wall Section
01/10/2008: Wall Section
01/11/2008: 3D Rendering
01/14/2008: 3D Rendering
01/15/07: Presentation Outline
01/16/07: Blog Updates
01/18/07: Mentor Contacts Updated
01/23/07: Log Updated, Mentor Contacts Submitted
01/24/07: Formal Report Update
01/28/07: Formal Report Update
01/29/07: Formal Report Update
02/01/07: MP3 Calendar created
02/04/07: Calendar updates
02/05/07: North Elevation drawing edited
02/06/08: Edited North Elevation Drawing
02/07/08: Edited South Elevation Drawing
02/11/08: Edited South Elevation Drawing
02/12/08: Edited East Elevation
02/13/08: Edited West Elevation
02/14/08: Edited West Elevation
02/15/08: Edited West Elevation
02/19/08: Edited East Elevation
02/21/08: Edited South Elevation
02/25/08: Prepared drawings for plotting.
02/27/08: Gathered materials.
02/29/08: Gathered materials, measured cuts.
03/03/08: Prepped materials.
03/04/08: Prepped materials.
03/05/08: Cut base of model.
03/06/08: Marked locations, property lines, house outline on base.
03/06/08: Mark post piles to be cut for foundation.
03/07/08: Begin cutting post piles for foundation.
03/10/08: Complete cutting post piles for foundation.
03/11/08: Begin marking Foamcore to be cut for floors.
03/12/08: Cut Foamcore for first floor and second floor.
03/13/08: Cut Foamcore for first floor walls.
03/14/08: Continue cutting Foamcore for first floor walls.
03/17/08: Finish cutting first floor exterior walls.
03/18/08: Completed press release.
03/19/08: Loaded materials to bring home, mark walls to be cut.
03/31/08: Continued cutting walls on band saw, broke said band saw. =(
04/01/08: cut walls on band saw
04/02/08: sanded edges of walls to create 45 degree angle
04/03/08: marked doors to be cut, cut doors on band saw
04/04/08: finished cutting pieces on band saw
04/05/08: assembled second floor walls, cut out windows
04/06/08: assembled first floor, pilings, and roof